What does 100 MW mean?
A megawatt measures power at a given moment. In this example, the computers use 100 MW.
The number usually refers to the information technology load: servers, processors, memory, storage and networking. It does not include all the equipment that keeps those computers running. Pumps move cooling water. Fans move air. Electrical equipment changes voltage and converts power. Lights, controls and security equipment also consume electricity.
The grid connection, cooling equipment and backup supply must all support that computer load. Each part needs enough capacity for the electricity entering the building and the heat leaving it.
The International Energy Agency's 2026 outlook estimates that data centres used 485 terawatt-hours (TWh) in 2025 and projects around 950 TWh in 2030. Those are global figures for data centres, not AI alone. At a local level, a single large project still needs a specific connection, cooling design and delivery schedule. A global growth forecast cannot establish whether a particular site is ready.
The main test
Establish how much electricity the utility can deliver and when. Then calculate the heat the building must remove.
How does 100 MW become a 138 MW grid request?
Data centres use a measure called power usage effectiveness, or PUE. It divides all electricity entering the building by the electricity used by the computers. A perfect building would have a PUE of 1.00, but real cooling and electrical equipment need power of their own.
In our middle example, PUE is 1.20. A 100 MW computer load needs 120 MW for the full building. Adding 15% planning headroom for growth, operating limits and design uncertainty gives a grid request of 138 MW.
| Step | Calculation | Result |
|---|---|---|
| Computers | Given design target | 100 MW |
| Full building | 100 MW × PUE 1.20 | 120 MW |
| Grid planning figure | 120 MW × 1.15 | 138 MW |
The 15% headroom is an assumption. The utility and electrical designer must set the figure for the site. In this example, a 100 MW supply cannot cover the computers and the supporting equipment.
Capacity, energy and reserve are different commitments
Headroom is capacity reserved for a design condition. It is not an instruction to consume 138 MW continuously, so it does not belong in the annual energy calculation as if it were an operating load. Equally, buying enough annual renewable electricity does not establish that the local network can deliver the required power at every instant. The connection agreement and energy procurement solve different problems.
How many high-power racks does that represent?
NVIDIA states that one GB200 NVL72 rack can use about 120 kW at full load. Each rack contains 18 compute nodes and 72 Blackwell graphics processors.See NVIDIA's rack power reference.
Dividing 100,000 kW by 120 kW gives 833.3, or 834 rack equivalents when rounded up. A real data centre may use different equipment. The calculation gives a reference for its electrical and cooling needs.
| Item | Reference amount | What the design must provide |
|---|---|---|
| AI racks | 834 at 120 kW each | Power, network connections, liquid cooling and service access. |
| Full building | 120 MW in the middle case | Transformers, switchgear, pumps, fans, controls and other support equipment. |
| Grid request | 138 MW with our headroom | A firm utility offer, delivery date and agreed backup arrangement. |
The 834 figure is a rounded power equivalence, not a bill of materials. Filling every rack at that reference rating would slightly exceed 100 MW, and a working cluster also needs storage, networking and other IT loads within the same budget. Dense racks make the electrical and thermal challenge visible, but floor area must also allow for maintenance, distribution equipment and safe access.
How much electricity does the building use in a year?
Power measures demand at a given moment. Energy measures use over time. One megawatt-hour (MWh) is one megawatt used for one hour.
Annual energy = computer load × PUE × 8,760 hours × average use.
We assume the computers average 90% of full load across the year. The table compares three PUE values.
| PUE | Full-building power | Annual electricity | Cost at €100/MWh |
|---|---|---|---|
| 1.10 | 110 MW | 867.2 GWh | €86.7M |
| 1.20 | 120 MW | 946.1 GWh | €94.6M |
| 1.40 | 140 MW | 1,103.8 GWh | €110.4M |
The middle case uses about 946.1 GWh per year. At the example price of €100/MWh, that costs about €94.6M each year. Reducing PUE from 1.40 to 1.10 saves about 236.5 GWh, or €23.7 million at the same price.
The electricity price is an example, not a quoted tariff. A commercial model would also need connection charges, taxes, demand charges and hedging costs.
Here, “90% use” means average electrical demand relative to the assumed full IT load. It does not mean the GPUs are doing useful work 90% of the time. Idle equipment can still draw power, and a cooling plant has loads that do not shrink in direct proportion to IT demand. Use measured load curves when moving beyond this screening calculation.
Where does the heat go?
Nearly all the electricity used by the computers becomes heat. A 100 MW computer load therefore creates roughly 100 MW of heat that must be moved from the chips to the outdoor air.
NVIDIA's reference rack needs about 120 kW of cooling capacity and uses direct liquid cooling. NVIDIA describes the cooling manifolds in its OCP design release. Water can carry much more heat than air, which is why modern AI racks use liquid close to the chips.
If water warms by 10°C while carrying away 100 MW, the basic heat equation gives a flow of about 2,388.9 litres per second. A real building divides this flow between many closed pipes, pumps and coolant distribution units.
ASHRAE reports that warm-water designs without chillers can approach PUE 1.10 and use very little cooling water in suitable climates. See ASHRAE's integrated design examples. The Open Compute Project recommends delivering coolant at 30°C or warmer as a durable design target. See the OCP coolant roadmap. Local weather determines whether dry coolers can reject the heat throughout the year.
What the cooling design must state
Record how much heat goes into liquid, the water temperatures, the pump power, the hottest outdoor condition, the water treatment plan and what happens after a leak or failed pump.
Liquid cooling does not tell you how much water a site consumes
A pipe can move thousands of litres a second without using up thousands of litres a second. The flow estimate above describes water circulating through the heat-transfer system. If that loop is closed, most of the same water returns to the pumps. The volume that must be replaced depends on leaks, maintenance and the way the building finally releases heat to the environment.
- ChipA cold plate receives heat from the processor.
- Rack loopCoolant carries heat to a distribution unit.
- Facility loopA heat exchanger passes heat to the building system.
- Heat rejectionDry coolers or an evaporative system release heat outdoors.
In an evaporative system, some water leaves as vapour while carrying heat away. Other water is discharged to control the concentration of dissolved minerals. A dry cooler transfers heat to outdoor air through a heat exchanger and avoids that evaporative mechanism, but its performance depends on outdoor temperature and the temperature the computers can accept. The US Department of Energy's cooling-water guide explains why the final heat-rejection stage matters.
This is why a claim of “liquid cooled” is incomplete. Ask for the annual water balance, the hottest-day operating case, the water source and the discharge requirements. A design that performs well in a cool season may need a different mode during a heatwave. A site with a limited water allocation must demonstrate that it can still operate within that allocation when demand is highest.
Read PUE alongside water use and useful work
PUE describes the overhead around the IT equipment. It does not measure how efficiently an algorithm uses a GPU, how much useful work the servers deliver, or the carbon intensity of the electricity. A facility can have excellent PUE while running an inefficient workload. Equally, an operating choice that reduces cooling electricity may increase water use.
The Department of Energy's data centre design guide treats IT, cooling, electrical distribution and heat recovery as connected design decisions. For a project review, request those measures together: facility energy, IT energy, water consumption and a workload-specific output measure. State each measurement boundary so that a good-looking ratio cannot hide an important cost.
What happens when the grid supply stops?
Computers cannot wait several minutes for a generator to start. Batteries or another fast supply must carry the building during the changeover or give the computers enough time to shut down safely.
At 120 MW, five minutes of full-building power equals 10 MWh of delivered energy. Our model assumes 90% discharge efficiency and uses only 80% of the battery capacity. That raises the installed battery to about 13.9 MWh.
Five minutes is only a bridge. The design must specify what happens after ten milliseconds, ten seconds, five minutes and four hours. It must also cover battery recharging and the loss of part of the backup supply.
The difficult part is making the systems work together
A capacity rating is a starting point. The operating question is whether the facility can maintain the required service while an ordinary component is unavailable. A pump will need maintenance. A breaker will need inspection. A cooling unit may fail during hot weather. Each event changes the capacity available to the computers.
Redundancy therefore needs a stated boundary. “N+1” means little unless the design defines the load N must support, identifies the extra unit, and shows that common pipes, controls, electrical paths or maintenance procedures do not defeat it. Additional equipment can also add losses and fixed loads. The energy model and the reliability model need to describe the same facility.
Follow a power interruption all the way to the workload
During an outage, keeping servers energised is only part of the problem. Cooling pumps, distribution controls and the necessary networking must also survive the transition. A battery with adequate stored energy can still be unsuitable if it cannot deliver the required instantaneous power. The five-minute example above establishes an energy requirement; it does not specify the inverter rating, electrical protection or thermal response.
The IT team has choices too. Some jobs can checkpoint and restart; other services must continue without interruption. A commissioning plan should connect those workload requirements to the electrical sequence and cooling behaviour. Ask what happens during the event, how the facility recovers, and how the backup system becomes ready for a second event before it has fully recharged.
A connection date is a commercial input
Ordering computing hardware before power and cooling are ready creates an expensive timing risk. Equipment can arrive while revenue is still impossible, warranties are running and the intended workload is changing. A phased opening can reduce exposure, but only if the utility offer, construction sequence and customer contracts all support that phase.
For that reason, a useful feasibility review ends with a dated capacity schedule: how much IT load can operate at each milestone, what evidence unlocks the next increment, and who owns the remaining dependency. The 138 MW planning figure in this article is an example to start that conversation. It cannot replace a utility study or a site-specific design.
What must be proven before construction?
Before detailed design, the computer plan, grid supply, cooling equipment and backup sequence must be consistent. These are the minimum records we would ask to see.
| Question | Evidence required |
|---|---|
| What will the computers draw? | Rack list, expected use, growth plan and power limits. |
| What will the utility deliver? | Signed capacity, connection design, delivery date and expansion terms. |
| Can the building distribute the power? | Electrical diagram, transformer and switchgear ratings, losses and protection study. |
| Can the building remove the heat? | A complete heat calculation for the hottest weather and failed equipment. |
| What happens during an outage? | Battery, generator or alternate-supply sequence with fuel and recharge requirements. |
| Can the owner afford to run it? | Electricity, grid, cooling, water, maintenance and equipment-replacement costs. |
If one of these answers is still an estimate with no owner or delivery date, the site is not ready for a 100 MW commitment.
Sources and assumptions
This illustrative model separates assumed inputs from vendor references. The article was expanded and its linked sources reviewed on 31 October 2026. Global demand context uses the IEA’s 2026 update; the GB200 rack is an explicit reference configuration, not a claim about every current AI system.
Model inputs
| Input | Value | Basis and limit |
|---|---|---|
| Computer load | 100 MW | Illustrative design target. |
| Power usage effectiveness (PUE) | 1.10, 1.20, 1.40 | Assumed cases; 1.20 is the middle case. |
| Average use | 90% of full load | Assumed annual average; the model scales facility power with computer load. |
| Operating year | 8,760 hours | A non-leap year; no separate outage allowance is applied. |
| Grid headroom | 15% | Planning assumption applied to facility power; the utility must set the actual requirement. |
| Rack power | 120 kW per rack | NVIDIA GB200 NVL72 full-load reference [2]; other rack designs differ. |
| Heat and coolant | 100 MW, 10°C rise | Assumes the full computer load becomes heat carried by water; heat split and coolant mixture may differ. |
| Water properties | 4.186 kJ/kg·K; about 1 kg/L | Simplified water heat capacity and density for the flow estimate. |
| Backup bridge | 5 minutes at 120 MW | Illustrative full-facility load; duration and supported loads require a site design. |
| Battery assumptions | 90% efficiency; 80% usable capacity | Assumptions used to size installed energy capacity. |
| Electricity price | €50, €100 and €150/MWh | Illustrative sensitivities; the article shows €100/MWh and excludes other charges. |
Source trail
- [1] IEA: Key Questions on Energy and AI, executive summary (2026)
- Location
- Updated data-centre electricity demand outlook.
- Supports
- The 2025 global demand estimate and the updated 2030 projection.
- Limit
- Global estimates and scenarios, not measurements or forecasts for this example facility.
- [2] NVIDIA: Mission Control administration guide, power FAQ
- Location
- Example 1: configuring a power domain for a GB200 NVL72 rack.
- Supports
- The approximate 120 kW full-load rack, 18 nodes and four GPUs per node.
- Limit
- A vendor reference configuration; actual equipment and operating loads may differ.
- [3] NVIDIA: GB200 NVL72 designs for the Open Compute Project (2024)
- Location
- Liquid cooling manifolds and floating blind mates.
- Supports
- The rack's direct-liquid-cooling design and approximately 120 kW cooling capacity.
- Limit
- A vendor description of one rack design, not a facility-wide cooling specification.
- [4] ASHRAE: AI data centre integrated design principles
- Location
- GB200 dry-cooled architecture comparison and case studies.
- Supports
- The cited PUE example and warm-water, chiller-less cooling discussion.
- Limit
- Examples depend on equipment, climate and operating conditions; PUE 1.10 is not guaranteed.
- [5] Open Compute Project: 30°C Coolant, revision 1.0 (2024)
- Location
- Page 25: cooling temperature and climate analysis.
- Supports
- The 30°C technology-cooling-system temperature discussed in the article.
- Limit
- The analysis uses stated operating and climate assumptions; it does not prove a chiller-less design works at every site.
- [6] US Department of Energy: cooling water efficiency opportunities
- Location
- Typical cooling system and water-efficiency opportunities.
- Supports
- The distinction between heat transfer and evaporative heat rejection.
- Limit
- A general guide; site water demand requires a local water balance.
- [7] US Department of Energy: energy-efficient data centre design guide (2024)
- Location
- IT systems, cooling, electrical systems and heat recovery.
- Supports
- Evaluating energy efficiency across the complete facility.
- Limit
- Design guidance, not a performance guarantee for this example.